  • Black utilities & energy
  • EU 2024/573
  • Global Warming Potential
  • Refrigerants
European Union flags in front of an office building in Brussels
A technician reading refrigerant pressures on a manifold gauge set
The EU F-gas Regulation 2024/573 sets the deadlines this roadmap works to. Every installation is assessed on the refrigerant it runs on.

The challenge

The EU F-gas Regulation 2024/573 sets phase-out dates and service bans for HFC refrigerants, and a PFAS restriction is on its way. The client wanted one plan for every cooling installation on its sites, from cold rooms of a few kilowatts to centrifugal chillers of several megawatts.

What we did

We started from the registered inventory and classified each installation by refrigerant, global warming potential (GWP) and the deadlines that apply to it. Each one received a timing, from "compliant" to "remove by date", and a method: drop-in, retrofit or system replacement. Two decision trees, one for direct-expansion systems and one for chillers, make the choice repeatable.

The inventory by urgency

  • 33Urgent, before 2030: GWP above 2,500 or HCFC
  • 368Medium term, 2030 to 2035: GWP 700 to 2,500
  • –The rest: no action needed now, or out of service

The result

A roadmap with a clear plan for every installation. The 33 urgent installations are tackled first. The medium-term group is retrofitted where that extends its life and replaced where it does not. For the long term, the direction is central hydronic systems on natural refrigerants: ammonia, propane and CO₂. The priority list now feeds targeted follow-up studies.